Time-to-Power market profile

Ohio / PJM

Use this page to decide whether Ohio / PJM belongs in active diligence now, which county and metro pages deserve the first trust check, and whether the Ohio / PJM Time-to-Power Pack is justified before deeper queue, utility, and land work begins.

Ohio / PJM is publicly sellable now, but this page should keep mixed-authority power caveats visible. It is not proof that every county, utility route, or PJM-related signal carries equal confidence or equal execution certainty.

Need the trust rules first? Review the public methodology.

Shortlist verdict

Ohio / PJM is worth shortlisting now

Ohio / PJM has enough current public proof to justify shortlist work now, but the next diligence step should focus on water risk, availability, and regulatory constraints.

Top opportunity

Power proxy supports shortlist potential

Top blocker

Water risk needs deeper validation

Fundamentals card

The market in 10 seconds

Market profile score
63.6 / 100
Overall verdict
Launchable
Confidence
Medium confidence (66 / 100)
Freshness
Current
Coverage count
29 counties / 1 metros
Publish source state
Current published release

Blocking-family cards

What deeper diligence should focus on

Power

Current

Confidence impact

Strengthens shortlist confidence

What this family means

Whether electricity route quality is strong enough to support shortlist confidence and near-term diligence.

Current read

Power proxy supports shortlist potential

4 power records informed this scope; queue and grid proxy signals support screening viability.

Connectivity

Current

Confidence impact

Strengthens shortlist confidence

What this family means

Whether fiber and network route quality support AI workload viability and carrier strategy.

Current read

Connectivity proxy supports network access posture

4 connectivity records indicate supporting network infrastructure proxies.

Water

Current

Confidence impact

Constraint signal is current

What this family means

Whether water availability and regulatory pressure could slow or disqualify candidate routes.

Current read

Water risk penalty applied

2 water context records contributed to a risk penalty for screening conservatism.

Hazards

Current

Confidence impact

Constraint signal is current

What this family means

Whether environmental and climate hazard exposure could create screening or underwriting drag.

Current read

Hazard risk penalty applied

6 hazard records indicate climate and event exposure requiring mitigation allowance.

Labor

Current

Confidence impact

Strengthens shortlist confidence

What this family means

Whether labor depth and workforce support improve buildability and operations confidence.

Current read

Labor support signal observed

2 labor records support staffing feasibility at county/metro scale.

Incentives

Current

Confidence impact

Strengthens shortlist confidence

What this family means

Whether policy and incentive support strengthen the route for deeper diligence and deployment.

Current read

Incentive bonus applied from available program registry

2 incentive records contributed to bonus scoring under current manual-first registry.

Timing truth

Ohio / PJM timing-risk posture

The timing basis for the Ohio / PJM Time-to-Power Pack. Proxy and unresolved rows are visible, not hidden.

Timing confidence

Medium

pack-level timing confidence grade

Queue-linked

No — proxy or unresolved rows present

whether all resolved rows are queue-linked

Direct vs proxy

80 proxy

sample row basis breakdown

Freshest as of

Unavailable

latest underlying TTPS refresh

Proxy basis present

Basis: Pack TTPS-band proxy basis

Current sample timing still depends on proxy basis rather than queue-linked evidence.

Timing is usable for pack framing, but proxy rows need visible separation.

How timing basis is derived

PJM queue data

direct

Ohio / PJM timing evidence uses the official PJM Planning API public export — a direct-fact queue copy. Row-level queue evidence supports stronger timing confidence than proxy-only markets.

Queue evidence freshness

Ohio / PJM: source freshness and process posture

Public summary from the queue evidence bridge. Full row-level evidence, exports, and decision memos stay inside the paid pack/watchlist flow.

Data freshness

Aging (22d old, as of Apr 25, 2026)

Data as of: Apr 25, 2026

Coverage

9,251 rows

9,251 timing signals · 0 change events

Confidence: High

Latest-change teaser

PJM Capacity Price declined 5.7% in PJM Western. PJM Western hub capacity prices declined 5.7% as new generation came online.

Last change date: Feb 24, 2026

Source contract

PJM Planning API interconnection queue export

Source slug: pjm-interconnection-queue

Truth class: Direct Fact

Source tier: Official Public Export

Limitation language

PJM queue evidence comes from the official public Planning API export. Use it as screening-grade decision support only; it does not guarantee parcel-level MW, utility-certified serviceability, interconnection timing, permitting outcomes, or power availability.

Need the row-level evidence?

The paid pack/watchlist includes shortlist rows, source appendix, exports, and decision-memo fields.

Get the Ohio/PJM Time-to-Power Pack

Trust Panel

Market trust panel

Use this panel to see what is direct fact, what is aging, what remains selective, and what still needs deeper diligence before you treat the shortlist as a market commitment.

Published

Mar 12, 2026, 02:09 PM GMT+2

Current published release

Confidence

Medium confidence (66 / 100)

How much trust to place in the current screening surface

Freshness

Current

What still looks current versus what needs a refresh check

Truth class

Published market-level screening object

Methodology power-ready-sites-methodology-v1.1.0

Evidence surfaced

240 evidence items

Signals kept visible instead of hidden behind a score

Timing basis

Pack TTPS-band proxy basis

How timing confidence is derived for this surface

Evidence type

Direct fact

Queue or official source data

Queue source

PJM Planning API interconnection queue export

Source tier: official public export

Last meaningful change

Feb 24, 2026

Date of last material signal update

Limitation statement

PJM queue evidence comes from the official public Planning API export. Use it as screening-grade decision support only; it does not guarantee parcel-level MW, utility-certified serviceability, interconnection timing, permitting outcomes, or power availability.

Family freshness strip

Review which source families are current, aging, or stale before treating the shortlist as current truth.

Power: CurrentConnectivity: CurrentWater: CurrentHazards: CurrentLabor Demographics: CurrentIncentives: Current

Evidence highlights

  • Power proxy supports shortlist potential
  • Connectivity proxy supports network access posture
  • Labor support signal observed
  • Incentive bonus applied from available program registry

Known unknowns

  • Public scope stays at market, county, and metro level; site-level precision remains outside this public object.

Limitations

  • Screening outputs do not guarantee utility deliverability or energization timing.
  • Parcel-level zoning, title, and entitlement diligence is outside this scoring model.
  • Incentive eligibility may depend on case-specific legal and tax review.

What this means

This market page is strong enough to guide where county, metro, and pack-level diligence should begin next.

What this does not mean

It does not confirm parcel-level deliverability, permitting certainty, or binding utility commitments.

Before you buy this Time-to-Power Pack

Verify the public proof layer first

Sample shortlist rows, export preview, and launchability evidence are visible before purchase. Use the public market, county, and metro pages to confirm this market deserves deeper diligence before you move into checkout.

1. Compare the strongest public pages

Start with the highest-signal county and metro pages in this market before deciding the Time-to-Power Pack is the next step.

Compare counties and metros

2. Review proof and methodology

Confirm the trust model, freshness posture, and what this market page does not claim before moving into a paid surface.

Review methodology on this page

3. Open the Time-to-Power Pack scope first

The market-specific offer page now carries the sample/proof language, Time-to-Power Pack scope, and buying route for this market.

View Ohio / PJM Time-to-Power Pack

Buy the Time-to-Power Pack or compare the strongest pages next

Sample shortlist rows, export preview, and launchability evidence are visible before purchase. Open the market-specific offer page first when you need proof and scope. Buy the pack when you need a concrete shortlist and export-ready diligence layer. Use the watchlist when you need recurring signal monitoring after initial screening.

Included counties

Use these county pages to separate real Ohio site-selection signal from broad PJM relevance before shortlist decisions get more expensive.

Included metros

Use these metro pages to judge whether the broader Ohio / PJM route is strong enough to support diligence now while keeping mixed-authority power caveats visible.

  • ColumbusScore 63.6

    Current published release

Methodology and trust model

Deterministic component model: opportunity components add upside, risk components apply deductions, and confidence is aggregated separately from score.

Methodology version: power-ready-sites-methodology-v1.1.0. This market summary covers published county and metro intelligence only.

Limitations

This score helps early screening, not permitting approval, utility commitment, or parcel-level constructability.

  • Screening outputs do not guarantee utility deliverability or energization timing.
  • Parcel-level zoning, title, and entitlement diligence is outside this scoring model.
  • Incentive eligibility may depend on case-specific legal and tax review.
Expand all limitations
  • Screening outputs do not guarantee utility deliverability or energization timing.
  • Parcel-level zoning, title, and entitlement diligence is outside this scoring model.
  • Incentive eligibility may depend on case-specific legal and tax review.
  • Pack preview summarizes screening signals and is not an investment recommendation.
  • Legacy fallback reconciliation is active for 1 site candidate(s); confidence is policy-downgraded.
  • Public market summaries include county/metro scorecards only; site candidates remain internal_only.