ERCOT Queue Intelligence
The ERCOT interconnection queue currently tracks 426+ GW of pending large-load projects across 1,846 rows. Queue posture and study progression are among the strongest public signals for time-to-power in Texas.
Source: ercot-queue-public-mirror
Truth class: curated_fact — secondary public mirror of official ERCOT GIS data
Source tier: public_mirror_of_official_gis
Validated rows: 1,846
Data as of: 2026-04-02
ERCOT queue evidence uses a secondary public mirror of official ERCOT GIS data. Use it as screening-grade decision support only; it does not guarantee parcel-level MW, utility-certified serviceability, interconnection timing, permitting outcomes, or power availability.
Queue evidence freshness
Public summary from the queue evidence bridge. Full row-level evidence, exports, and decision memos stay inside the paid pack/watchlist flow.
Data freshness
Stale (45d old, as of Apr 2, 2026)
Data as of: Apr 2, 2026
Coverage
1,846 rows
1,846 timing signals · 0 change events
Confidence: Medium
Latest-change teaser
ERCOT Spot Price rose 16.8% in ERCOT Houston. ERCOT Houston hub spot prices increased 16.8% week-over-week due to higher demand and lower wind output.
Last change date: Feb 24, 2026
Source contract
ERCOT public mirror of official GIS queue data
Source slug: ercot-queue-public-mirror
Truth class: Curated Fact
Source tier: Public Mirror Of Official Gis
Limitation language
ERCOT queue evidence uses a secondary public mirror of official ERCOT GIS data. Use it as screening-grade decision support only; it does not guarantee parcel-level MW, utility-certified serviceability, interconnection timing, permitting outcomes, or power availability.
Need the row-level evidence?
The paid pack/watchlist includes shortlist rows, source appendix, exports, and decision-memo fields.
Queue congestion level
Total pending MW and project count indicate how competitive the queue is for new entrants.
Study phase distribution
Whether projects are concentrated in early intake, system impact, or late-stage phases.
Data center project share
How many large-load queue entries are data-center-related vs generation or industrial.
Withdrawal patterns
Withdrawn projects may free capacity or indicate systemic process issues.
Geographic concentration
Where in Texas queue entries cluster — useful for identifying saturated vs underserved zones.
Transmission owner distribution
Which transmission service providers carry the heaviest queue loads.
This page provides market-level queue posture and freshness signals. Full row-level queue evidence, county-specific screening, change history, and source appendix are available in the paid Time-to-Power Pack.