ERCOT Queue Intelligence

ERCOT Large Load Queue

The ERCOT interconnection queue currently tracks 426+ GW of pending large-load projects across 1,846 rows. Queue posture and study progression are among the strongest public signals for time-to-power in Texas.

Source and data quality

Source: ercot-queue-public-mirror

Truth class: curated_fact — secondary public mirror of official ERCOT GIS data

Source tier: public_mirror_of_official_gis

Validated rows: 1,846

Data as of: 2026-04-02

ERCOT queue evidence uses a secondary public mirror of official ERCOT GIS data. Use it as screening-grade decision support only; it does not guarantee parcel-level MW, utility-certified serviceability, interconnection timing, permitting outcomes, or power availability.

Queue evidence freshness

Texas (ERCOT): source freshness and process posture

Public summary from the queue evidence bridge. Full row-level evidence, exports, and decision memos stay inside the paid pack/watchlist flow.

Data freshness

Stale (45d old, as of Apr 2, 2026)

Data as of: Apr 2, 2026

Coverage

1,846 rows

1,846 timing signals · 0 change events

Confidence: Medium

Latest-change teaser

ERCOT Spot Price rose 16.8% in ERCOT Houston. ERCOT Houston hub spot prices increased 16.8% week-over-week due to higher demand and lower wind output.

Last change date: Feb 24, 2026

Source contract

ERCOT public mirror of official GIS queue data

Source slug: ercot-queue-public-mirror

Truth class: Curated Fact

Source tier: Public Mirror Of Official Gis

Limitation language

ERCOT queue evidence uses a secondary public mirror of official ERCOT GIS data. Use it as screening-grade decision support only; it does not guarantee parcel-level MW, utility-certified serviceability, interconnection timing, permitting outcomes, or power availability.

Need the row-level evidence?

The paid pack/watchlist includes shortlist rows, source appendix, exports, and decision-memo fields.

Get the Texas Time-to-Power Pack

What the ERCOT queue tells data center developers

Queue congestion level

Total pending MW and project count indicate how competitive the queue is for new entrants.

Study phase distribution

Whether projects are concentrated in early intake, system impact, or late-stage phases.

Data center project share

How many large-load queue entries are data-center-related vs generation or industrial.

Withdrawal patterns

Withdrawn projects may free capacity or indicate systemic process issues.

Geographic concentration

Where in Texas queue entries cluster — useful for identifying saturated vs underserved zones.

Transmission owner distribution

Which transmission service providers carry the heaviest queue loads.

Public vs paid data

This page provides market-level queue posture and freshness signals. Full row-level queue evidence, county-specific screening, change history, and source appendix are available in the paid Time-to-Power Pack.

Limitations

  • Queue position does not guarantee interconnection approval or energization date.
  • ERCOT connect-and-manage policy may change — historical fast-track paths are not guaranteed going forward.
  • This data uses a public mirror, not direct ERCOT MIS ingestion. Some entries may lag the official GIS report.
  • County-level queue attribution depends on project-reported location, which may be approximate.
  • This is screening-grade decision support, not a substitute for utility engineering studies.

Get Texas time-to-power intelligence