Crypto-to-AI Conversion Calculator
Estimate conversion costs, timeline, and economics for your mining facility.
Site Parameters
50MW
Conversion Estimate
AI Usable MW
28
(45% shrink)
Total CapEx
$336.0M
$12.0M/MW
Timeline
18
months (12-24)
vs Greenfield
70%
faster (42 mo saved)
CapEx Range (±15%)
Low
$285.6M
High
$386.4M
Economics Improvement
NOI Margin15%ā80%(+65pp)
EV/EBITDA Multiple8xā22x
Disclaimer: These estimates are based on industry benchmarks (TeraWulf $8-10M/MW, Northern Data MW shrink disclosures). Actual costs depend on site-specific factors including existing infrastructure condition, local labor costs, and supply chain timing.